Job title: SharePoint Migration - REQ-DASOBO-000220101
Location: Salem, OR.
Duration: 12+ Months
Client: Oregon Department of Justice (DOJ)
Note: Candidate Must Be Local - Candidate must be within 100 miles
The Oregon Department of Justice (DOJ) is seeking quotes for tools, services, and implementation support to migrate content from its current repositories including Alfresco, network drives, and selected SharePoint Online sites into a modern Microsoft SharePoint Online environment within the Microsoft 365 Government Community Cloud (GCC). This migration is a key component of DOJ s enterprise content management (ECM) modernization initiative, supporting DOJ s Cloud First strategy and aligning with the Legal Tools Program (LTP) roadmap.
The Legal Tools Program is DOJ s strategic initiative to modernize legal case management and document workflows. As part of this program, DOJ is implementing JusticeNexus a Dynamics 365-based platform that will serve as the authoritative system for case and matter management. The [GS1] migration of legal case-related documents will be structured to ensure seamless integration and alignment with JusticeNexus folder patterns, metadata, and security requirements. This alignment is critical to maintain data integrity, compliance, and operational continuity across DOJ s legal workflows.
Number
Name
Deliverables
Description
Start Date
End Date
1
4.5.1
TOM & Information Architecture Validation
TOM & Information Architecture Validation
01/01/2027
01/01/2028
2.1
4.5.2
Repository Inventory & Readiness Assessment
Repository Inventory & Readiness Assessment
01/01/2027
01/01/2028
2.2
4.5.2
Repository Inventory & Readiness Assessment
Repository Inventory & Readiness Assessment
01/01/2027
01/01/2028
3.1
4.5.3
Migration Strategy & Scheduling
Migration Strategy & Scheduling
01/01/2027
01/01/2028
3.2
4.5.3
Migration Strategy & Scheduling
Migration Strategy & Scheduling
01/01/2027
01/01/2028
4.1
4.5.4
Pilot Migration Execution & Validation
Pilot Migration Execution & Validation
01/01/2027
01/01/2028
4.2
4.5.4
Pilot Migration Execution & Validation
Pilot Migration Execution & Validation
01/01/2027
01/01/2028
5.1
4.5.5
Production Migration Execution & Delta Migration
Production Migration Execution & Delta Migration
01/01/2027
01/01/2028
5.2
4.5.5
Production Migration Execution & Delta Migration
Production Migration Execution & Delta Migration
01/01/2027
01/01/2028
6.1
4.5.6
Migration Validation & Acceptance
Migration Validation & Acceptance
01/01/2027
01/01/2028
6.2
4.5.6
Migration Validation & Acceptance
Migration Validation & Acceptance
01/01/2027
01/01/2028
7
4.5.7
Training and Knowledge Transfer (include separate pricing for each sub-item below)
Training and Knowledge Transfer (include separate pricing for each sub-item below)
01/01/2027
01/01/2028
7.1
4.5.7.1
OCM Strategy & Communications
OCM Strategy & Communications
01/01/2027
01/01/2028
7.2
4.5.7.2
End-User Training Plan
End-User Training Plan
01/01/2027
01/01/2028
7.3
4.5.7.3
Information Services & Site Owners Training
Information Services & Site Owners Training
01/01/2027
01/01/2028
7.4
4.5.7.4
End-User Readiness & Hypercare
End-User Readiness & Hypercare
01/01/2027
01/01/2028
7.5
4.5.7.5
Knowledge Transfer & Acceptance
Knowledge Transfer & Acceptance
01/01/2027
01/01/2028
8.1
4.5.8
Migration Tooling & Pipeline Configuration
Migration Tooling & Pipeline Configuration
01/01/2027
01/01/2028
8.2
4.5.8
Migration Tooling & Pipeline Configuration
Migration Tooling & Pipeline Configuration
01/01/2027
01/01/2028